OPA Board hears of four Community Hall options and costs from Bill Rakow. 1/30/2008.
Here are the Community Hall options presented :
- Maintain the existing facility $305,000 ??? -- includes roof repair, correct code violations, fire department stays. 7,830 SF of OPA space.
- Complete Rehab of existing facility -$1.2 million to $1.6 million. Fire department moves out, new roof, new walls and siding, new mechanical systems, reconfigure offices and meeting space, new rest rooms and kitchen. 10,800 SF of space for OPA.
- Build new Community Hall and tear down old - $2.2 million to $2.4 million. 14,000 to 16,000 SF of new space.
- Build New Community Hall and maintain existing building -- Cost of item 3 and item 1 combined. Roughly $3 million.