The project is expected to proceed in a partial manner for a cost of around $800,000 with OPA contributing about $250,000.
That said, this project was a failure before the first dime was spent. Why? Because someone, perhaps at the county level, misled OPA folks to believe the increased water flow from the project could be dumped into a pond on the old golf course property. Now $800,000 will be spent with no place to take the water flow. Where will the increased flows from pipe and ditch improvements be directed? Maybe someone has an answer but I have not heard it. In fact, the board members never even asked the question. |
||||||
|
||||||