![]() ![]() Section 5: OPA Board Subject: Community Center Contract Msg# 387918
|
||||||
I choose to be more optimistic that settlement will be a compromise by mutual agreement. I agree. However, that does not mean a settlement could not push $1 million, depending on the stage of construction when stopped. At this point we have probably spent around $250,000 not even considering Blades. |
||||||
|
||||||
For reference, the above message is a reply to a message where: Joe, We agree. However, with all the speculations most being worst case scenarios, I choose to be more optimistic that settlement will be a compromise by mutual agreement. Norm |
Calendar |
![]() 3/29/2025 - 9:00 A.M. |
![]() 4/26/2025 - 9:00 A.M. |
![]() 5/24/2025 - 9:00 A.M. |
![]() 6/28/2025 - 9:00 A.M. |
![]() 7/26/2025 - 9:00 A.M. |