Section 5: OPA Board Subject: Community Center Contract Msg# 389665
|
||||||
Janet Your contingency figure of 14% (or $900,000) is 14% of approx 6.4m-about twice the contingency figures others are using. What makes you think we need to add such a large contingency number? Respectfully Fritz Johnson |
||||||
|
||||||
For reference, the above message is a reply to a message where: Why not post a message with your detailed list of all costs to show it is over $6 Fritz, Fritz, Ok. It concerns me that this information didn't get seen. I have also included the correct defination of just the "construction cost" per prospectus: The 3.9 Million Construction Budget Includes the Construction Costs + 5.3M- 5.5M Site Work / Blades 3,912.500 $741,539 Plus Addition Costs May Also Include,Soil Replacement If Needed
Regards, Janet |
Calendar |
OPA Board Meeting - Golf Clubhouse
1/25/2025 - 9: A.M. |
OPA Board Meeting - Golf Clubhouse
2/22/2025 - 9:00 A.M. |
OPA Board Meeting - Golf Clubhouse
3/29/2025 - 9:00 A.M. |
OPA Board Meeting - Golf Clubhouse
4/26/2025 - 9:00 A.M. |
OPA Board Meeting - Golf Clubhouse
5/24/2025 - 9:00 A.M. |